Guys,
In P3 3.1 is that possible to calculate the current total minus the target total float and put the answer in the column. The reason Im using this option because if I use the varaiance target finish only give me the change of duration comparison not the slippage impact of the project.
Regards,
jeff
In P3 3.1 is that possible to calculate the current total minus the target total float and put the answer in the column. The reason Im using this option because if I use the varaiance target finish only give me the change of duration comparison not the slippage impact of the project.
Regards,
jeff