Hi,
Im somewhat newer to P3. Ive got a P3 schedule to manage and to progress, but Id like to see the actual and projected against the planned bars.
I think I have my Target schedule set (BASE) and the one I will be progressing set (PROG). I still only see my PROG schedule.
What am I doing wrong?