Hi all!
I have this problem with primavera 5, i work in construction and we regularly need to set up different working calendar for the same project. For exemple 10 hours/day and 20 hours/day, meening activity done in one or two shifts.
The problem im facing is as follows:
- default setting is 10 hours/day,
- Planned duration for an activity is 10 days but with 20hours/day calendar, P5 end date is calculated as 5 days not 10 days.
How can we work in day units using multiple calendars in P5, we actually did not have this issue in P3?
Thanks for the help
I have this problem with primavera 5, i work in construction and we regularly need to set up different working calendar for the same project. For exemple 10 hours/day and 20 hours/day, meening activity done in one or two shifts.
The problem im facing is as follows:
- default setting is 10 hours/day,
- Planned duration for an activity is 10 days but with 20hours/day calendar, P5 end date is calculated as 5 days not 10 days.
How can we work in day units using multiple calendars in P5, we actually did not have this issue in P3?
Thanks for the help