This has probably been asked before, but I will ask again. I have a chart in which I am comparing planned against actual. the planned start is 05.06.07 the duration is 54 days and the planned finish is 17.08.07. I have run a macro giving the planned % as 35. The actual start is 25.06.07, the actual % is 33% this gives a remaining duration of around 36 days. However, the progress bar has moved to 25.06.07 thats ok, but the progress infill goes to a third of the bar but the end date for the bar is still 54 days away from the 25.06.07. It should be 36 days from 02.07.07. If I have done a third of the duration in the first week surely the duration should adjust itself to reflect the remaining duration ??
Andrew
Andrew