What happens if you use 2 different calendars in one project ; I mean :
=> In general, there is one Calendar which is put by default on each activity you create.
=> You can choose another calendar (with specific days Off, or vacations for example) for some activities.
In that case, what happens with Remaining Duration on the WBS Element ? It seems the remaining Duration is calculated with the Calendar by Default. Is it possible to change it for one or a few WBS elements of the project ?
I have not any "Calendar Column" in WBS view.
Hope to read you soon,
Regards.