Hi,
I am using Primavera Version 5.0.
I have been trying to re-baseline a schedule that is in progress but have had problems with activities that are either in-progress or 100% complete - the baseline dates being saved are not the same as the start/finish dates.
P.S. Baseline dates for actvities that are not started seem to working perfectly?
Any suggestions?
Thanks.
Roger.