I often find some wrong Remaining Early Start Dates of resources on LOE Activities that have already begun.
We have this problem when we select the field "Drive Activity Date".
If we do not select it, we notice that it is the Finish Date of the Resource that is wrong.
Is there any way to solve this problem ?
We have this problem when we select the field "Drive Activity Date".
If we do not select it, we notice that it is the Finish Date of the Resource that is wrong.
Is there any way to solve this problem ?