Folks,
I have serious problem with Remaining Resource calculation after first update of activity
Senario
Activity A - Typ Unit Price % unit() duration 5 day budgeted unit 100
first progress 20% shows remaining as 80 (Correct)
second Progress 40% shows remaining out of wack!!
Problem ( Resource forecast based on the Progress is Wrong)
one solution put progress as physical and update the actual , works for single resource but for multi resource activity spread actual among resources equally ( as an example ) 20= actual (2 res divide 10 for each regardless of their Ratio)
Please advice
I have serious problem with Remaining Resource calculation after first update of activity
Senario
Activity A - Typ Unit Price % unit() duration 5 day budgeted unit 100
first progress 20% shows remaining as 80 (Correct)
second Progress 40% shows remaining out of wack!!
Problem ( Resource forecast based on the Progress is Wrong)
one solution put progress as physical and update the actual , works for single resource but for multi resource activity spread actual among resources equally ( as an example ) 20= actual (2 res divide 10 for each regardless of their Ratio)
Please advice