Help fellow planners,
I am currently trying to finalise & justify a couple of programmes here in Bucharest.
One project is for 300 apartments built in a mixture of 12 and 5 stoey towers. These are for private sale.
I am able to assess programme durations for individual apartments but am unsure as to the overall completion rate achievable.
In the UK I would work on the basis of about 4 - 6 apartments per week. I am being pushed by a Project Manager with an eye on prelims and Client wishes to increase this rate on the basis that completion is determined by access rate (Number of apartments avaialable on completion of floor)
Has anyone got any views on overall completion date and perhaps level of site management required to achieve higher rates. PM wants 10-16 apartments per week and there are max 12 on a block floor.
I am currently trying to finalise & justify a couple of programmes here in Bucharest.
One project is for 300 apartments built in a mixture of 12 and 5 stoey towers. These are for private sale.
I am able to assess programme durations for individual apartments but am unsure as to the overall completion rate achievable.
In the UK I would work on the basis of about 4 - 6 apartments per week. I am being pushed by a Project Manager with an eye on prelims and Client wishes to increase this rate on the basis that completion is determined by access rate (Number of apartments avaialable on completion of floor)
Has anyone got any views on overall completion date and perhaps level of site management required to achieve higher rates. PM wants 10-16 apartments per week and there are max 12 on a block floor.