Gents,
Im facing a problem while updating the actual resource units to an in progress activity in Primavera Ver 5.0. When ever Im Scheduling the actual unit is either showing ZERO or going back to the previous period update actual value. I didnt store period performance last time.
Example : ENWP51079 - Fabrication of Intermediate Tank has 2748 manhours as budget. Last update was 69 hrs and this time I want to change to 499 hrs. I keyed in the actual this period hrs. When scheduling The actual is going back to 69 hrs.
Please help.
Regards
Dinesh