Hi there everybody
would anyone be able to explain to me how I can remove a constraint on a Finish Date when a project has been copied with constraint dates attached.
The star appears next to the date indicating a constraint but there is no constraint shown under the status tab. I have tried various things to remove these constraints but to no avail. These constraints are giving me huge negative floats on certain activities.
thanx