I am building up a plan at the moment and I have 2 tasks with no successor and within the project date but showing zero float.
I would expect the float to be the difference between the 2 dates and not zero. Is this the way of MSP or is there a switch to turn this off?
I would expect the float to be the difference between the 2 dates and not zero. Is this the way of MSP or is there a switch to turn this off?