To al LEVEL I Planners
Developing a Project FEED phase where the BEST information that I have is:
- Major Equipment LIST
- PFDs (in progress)
- PIDs (in progress)
HOW CAN I assess duration for main project phases such as:
ENGINEERING
CONSTRUCTION
Is there any INDICATOR that may give us rough duration of phases mentioned above based on total tagged equipment. OR MAY BE another indicator between total PIDs and duration of above PHASES.
Waiting comments
Thanks
carmen