Has anyone ever created a global change to remove Actual dates and percent complete.
I am using a starting a new project (Turnaround) and have a historical project but I need to remove the actual start and end dates as well as making the percent complete zero.
This will allow me to copy and paste various parts of the old schedule into my new schedule.