Is there any recommendation on using relationships in pm software. For example the difference between using FS with minus lag or SS with positive lag.
Or that oil/gas recommend laddering so activities with a start to start should also have a finish to finish to complete before moving to successor activity.
Any papers on the subject would be great
thanks
Or that oil/gas recommend laddering so activities with a start to start should also have a finish to finish to complete before moving to successor activity.
Any papers on the subject would be great
thanks