I have assigned a resource for rollup purposes - called "Points". No other resource assigned.Cost=$1/hr
I use physical %.,for progress updates.
I have assigned a profile for points same in Baseline & Current Files.
I need to report Plan % vs Actual % by WBS.
For Actual I use Performance %
Activity & Band Summaries by WBS are excellent.
For Plan I use Schedule %.
At WBS level Plan is correct (Takes from Profile)
But at Activity Level the Plan is WRONG. It just uses the Duration based Plan %.
What I need is Plan % from Profile both at the activity Level & WBS Level
Anyone can hep or face same problem? Solution appreciated.
I use physical %.,for progress updates.
I have assigned a profile for points same in Baseline & Current Files.
I need to report Plan % vs Actual % by WBS.
For Actual I use Performance %
Activity & Band Summaries by WBS are excellent.
For Plan I use Schedule %.
At WBS level Plan is correct (Takes from Profile)
But at Activity Level the Plan is WRONG. It just uses the Duration based Plan %.
What I need is Plan % from Profile both at the activity Level & WBS Level
Anyone can hep or face same problem? Solution appreciated.