Does anyone know how to change the duration calculation when you change calendar after the project has been set up.
eg.
I have a plan that was set up using a 1-8-5 calendar, I have changed the activities to a 2-10-7 calendar, but the duration still shows using a 1-8-5 calendar.
Cheers
Dave
eg.
I have a plan that was set up using a 1-8-5 calendar, I have changed the activities to a 2-10-7 calendar, but the duration still shows using a 1-8-5 calendar.
Cheers
Dave