I am trying to apply a single new Calendar ID, that comprises a 2x10x6 (2 shifts; 10 hours/shift; 6 days/week)work shift arrangement, with a 2 hour gap between shifts
Shift 1: start 07:00 finish 17:00
Shift 2: start 19:00 finish 05:00
I am not sure if P3 can show this separate work shift arrangement for one Calendar ID.
Appreciate anyones help on this one.
Shift 1: start 07:00 finish 17:00
Shift 2: start 19:00 finish 05:00
I am not sure if P3 can show this separate work shift arrangement for one Calendar ID.
Appreciate anyones help on this one.