Hello Fellow Planners,
I am filtering by critical path but seem to have some gaps!
Have found these are elapsed duration tasks - is there a reason Asta does not show these in a critical path?
Can any one tell me how to turn on so they show in path?
Kind regards,
craig Adams
I am filtering by critical path but seem to have some gaps!
Have found these are elapsed duration tasks - is there a reason Asta does not show these in a critical path?
Can any one tell me how to turn on so they show in path?
Kind regards,
craig Adams