Hi, I have a project with resource constraint and I want to solve that without increasing my resource quantity than I had a problem with as late as possible constraint after I finished my schedule in as soon as possible constraint for all activities I leveled my project but not for activities which have available slack I leveled all of them. Than my project duration increased after the leveling operation I tried to make all my activities as late as possible but MS Project take my previous project duration and make my activities as late as possible I mean it’s clearing leveling and turns back. When I try to make my activities as late as possible after leveling I can manage to do them if I do one by one manually but after that a new problem occurs when I try to take S-CURVES It gives the cumulative cost for the first project duration.
Would you please help me about this problem if you want I can send you sample project.