Further to my query, I have got the file which is having the problem of incorrect calculation.
The problem is calendar can only accept 10 non working days. Once you enter the 11th day it moves by 4 extra days showing the incorrect contract period.
Alex can you please send me your email address again to send the file.
I would like to send the file to any other person who can help me to resolve this issue.