I am trying to buid a programme where the resources are driving the schedule which I have managed to do. All good so far. My problem lies when an entire acivity does not fit in to the remaining work time specified in the calendar. I want the activity to only start if there is enough time for it to finish in any given shift/opportunity of work.
I have gone back to basics in a hope of getting the programme to work! Ive read the manuals, researched the net, asked many people yet nobody seems to be able to answer me this one.
The project planning unit is in hours and each activity lasts for 12 hours.
Ive started off with one driving resource assigned to each activity which has a unit of 1 and a limit of 1.
My Global Calendar has 2 shifts per day at 12 hours per shift. I have set up my calendar to work weekends only for the full 48hrs.
This means 4no. activities fit in to each weekend where I have specified work time, perfect and all seems to work. However, if I reduce the work time in the calendar for any particular weekend to say 40hrs for example, 3no. activities fit perfectly in to this weekend and are followed by 8hrs of the next activity with the remaining 4hrs in the next available weekend (in reality this is a piling rig so it cant be split like this).
How can I stop these activities from splitting? I have specified 0 Splits using the Level function?
Any help would be most appreciated.
Regards
J
I have gone back to basics in a hope of getting the programme to work! Ive read the manuals, researched the net, asked many people yet nobody seems to be able to answer me this one.
The project planning unit is in hours and each activity lasts for 12 hours.
Ive started off with one driving resource assigned to each activity which has a unit of 1 and a limit of 1.
My Global Calendar has 2 shifts per day at 12 hours per shift. I have set up my calendar to work weekends only for the full 48hrs.
This means 4no. activities fit in to each weekend where I have specified work time, perfect and all seems to work. However, if I reduce the work time in the calendar for any particular weekend to say 40hrs for example, 3no. activities fit perfectly in to this weekend and are followed by 8hrs of the next activity with the remaining 4hrs in the next available weekend (in reality this is a piling rig so it cant be split like this).
How can I stop these activities from splitting? I have specified 0 Splits using the Level function?
Any help would be most appreciated.
Regards
J