Guys/Girls, I need your help i am preparing rundown curves for a number of commissioning projects, some of the projects are resourced some are task driven with no resources.
I can produce the baseline curves and the actual progress and the forecast to completion curves using remaining manhours, for the task driven schedule i am trying to use total float remaining each month to give me a forecast to completion rundown curve and this is not working out effectively, if i try using an average over the last 4 months that is giving me a curve but of linear proportion,
Has anybody any idea of the best way to produce this
I can produce the baseline curves and the actual progress and the forecast to completion curves using remaining manhours, for the task driven schedule i am trying to use total float remaining each month to give me a forecast to completion rundown curve and this is not working out effectively, if i try using an average over the last 4 months that is giving me a curve but of linear proportion,