1.What is the best way to indicate the procurement activities in the program.Especially where material lead time is high and the same is required before a planned activity can start.
eg submittals,approvals,order,___ FS(procurement lead time as dummy activity)-Delivery activity
Showing procurement lead time as dummy activity is better or to split it and show it as manufacturing/procurement/shipment activities.
What are the advantages and disadvantages in the above.
2.What is the best method to show procurement of material for the material locally available.
eg 1) PROCUREMENT,FABRICATION AND DELIVERY OF AIRCONDITIONING DUCTING IN A MULTISTOREY BUILDING - 40 storeys.
2) Procurement of various materials like pipes for firefighting ,watersupply drainage,electrical conduits for various floors of the above building
Is One Delivery bar with ss relationship with lag to the the installation of the various above activity enough.
Are the procurement of such activities required to be shown in the schedule ?
eg submittals,approvals,order,___ FS(procurement lead time as dummy activity)-Delivery activity
Showing procurement lead time as dummy activity is better or to split it and show it as manufacturing/procurement/shipment activities.
What are the advantages and disadvantages in the above.
2.What is the best method to show procurement of material for the material locally available.
eg 1) PROCUREMENT,FABRICATION AND DELIVERY OF AIRCONDITIONING DUCTING IN A MULTISTOREY BUILDING - 40 storeys.
2) Procurement of various materials like pipes for firefighting ,watersupply drainage,electrical conduits for various floors of the above building
Is One Delivery bar with ss relationship with lag to the the installation of the various above activity enough.
Are the procurement of such activities required to be shown in the schedule ?