in p3e/c 4.1, one UDF (say wtd_value) has been defined for activities. Now I want to copy the value of above UDF in budgeted unit for a specific resource through global change. But in global change screen for resource assignment, above UDF (wtd_value) is not appearing. Kindly help me.
Regards
Regards