Hi,
Following are the points:
1.Remeasured Contract.
2.10 Nos of specific windows clearly shown in the design drawings.
3. No corresponding item for the specific windows in B.O.Q. although items for different windows exists.
4. Not included in Tenders Adjustment schedule by Contractor.
5. No related querry was answered during Tender Stage.
Question : Is the execution of 10 Nos of windows falls under Variation ?
If no then how the contractor would get paid for the work ?
Following are the points:
1.Remeasured Contract.
2.10 Nos of specific windows clearly shown in the design drawings.
3. No corresponding item for the specific windows in B.O.Q. although items for different windows exists.
4. Not included in Tenders Adjustment schedule by Contractor.
5. No related querry was answered during Tender Stage.
Question : Is the execution of 10 Nos of windows falls under Variation ?
If no then how the contractor would get paid for the work ?