Why is it that in Activity Usage Profile, P3ec does not reflect the actual hours used by a Resource. Instead it distributes the hours used equally.
As an example:
Activity "A" with Resource ID "PF" assigned:
Budgeted Units=200hrs spread equally in 4 weeks (50hrs/wk)
Act type = Task Dependent
Dur type = Fixed Dur & Units
% complete type = Physical
When progressing activity "A" using the following actual values:
Week1 = 25hrs; Week2 = 75hrs; Week3 = 40hrs & Week4 = 60hrs, the Activity Usage Profile shows an actual hours usage of 50hrs/wk (total=200hrs) as if activity A has progressed according to plan with respect to planned hrs/wk.
Are there any settings or options in P3e that I missed for me to get the correct Usage Profile.
Thanks for all the help.
As an example:
Activity "A" with Resource ID "PF" assigned:
Budgeted Units=200hrs spread equally in 4 weeks (50hrs/wk)
Act type = Task Dependent
Dur type = Fixed Dur & Units
% complete type = Physical
When progressing activity "A" using the following actual values:
Week1 = 25hrs; Week2 = 75hrs; Week3 = 40hrs & Week4 = 60hrs, the Activity Usage Profile shows an actual hours usage of 50hrs/wk (total=200hrs) as if activity A has progressed according to plan with respect to planned hrs/wk.
Are there any settings or options in P3e that I missed for me to get the correct Usage Profile.
Thanks for all the help.