Hi,
I am using MSP 2000 and my question is the following:
I made a combined view which shows on the upper side a table with the pending tasks for a resource, and on the lower side the resource graph.
The main user of this view needs to see, next to each task, his predecessors and the status of them on a quick an visual way.
I tried with the Relationship Diagram, but it only shows the predecessors and sucessors, not their status (I only need if the task is completed or not).
is this possible?
Thanks.
Álvaro Gómez
Planning Engineer
Spain
I am using MSP 2000 and my question is the following:
I made a combined view which shows on the upper side a table with the pending tasks for a resource, and on the lower side the resource graph.
The main user of this view needs to see, next to each task, his predecessors and the status of them on a quick an visual way.
I tried with the Relationship Diagram, but it only shows the predecessors and sucessors, not their status (I only need if the task is completed or not).
is this possible?
Thanks.
Álvaro Gómez
Planning Engineer
Spain