I am importing a P3 (Version 3.1) project into P3e(Version 4.1), and I am splitting this project among the various lowest nodes of the EPS.
The problem I am facing is that the highest level of the imported WBS comes under the lowest nodes in the EPS and I want to remove the WBS highest level as it should the same as lowest in the EPS. In other words, I am having two duplicate nodes (EPS and WBS).
Any suggestion on resolving this issue would be appreciated.
Thanks.