I am currently working on a tender where the client states
" The employer has selected the use of Primaverea Teamplay Version 4 software to contain and manage the programme information"
I am preparing a tender programme for the project which is circa £200m in the uk with 4 separate sites, all sites running concurrently. The project is esentially traditional construction Concrete and steel frame containing a process operation.
I would normally use either Power Project 8, suretrak or P3, can anyone advise on the compatiblity of the above with Teamplay.
Thanks Andy
" The employer has selected the use of Primaverea Teamplay Version 4 software to contain and manage the programme information"
I am preparing a tender programme for the project which is circa £200m in the uk with 4 separate sites, all sites running concurrently. The project is esentially traditional construction Concrete and steel frame containing a process operation.
I would normally use either Power Project 8, suretrak or P3, can anyone advise on the compatiblity of the above with Teamplay.