I have a CTR that has a total dollar value with the cost being distributed over time in months, non-linear.
How can I create a task in ms project 2002 and distribute that cost over time equal to the CTR.
One way I can think of is to hard date milestones set to the same months as the CTR and assign cost to each milestone.
I have looked at task usage and the spreadsheet associated with it but I cannot enter cost in the spraedsheet.
Regards, Kelly