Hi all,
I have copied the original baseline of a schedule and applied actuals to this so it is shown on schedule this gives a duration percent complete of 8.45%
( we want to compare duration % complete on the baseline against the current plan duration % complete )
Can anyone tell me why in P3e when i attach the baseline, the duration percent complete on the baseline changes and matches identically to the current schedule and shows 4.5% although when it is detached it shows 8.45 % ????
Also, what is Schedule Percent Complete
Regards
confused guest !
I have copied the original baseline of a schedule and applied actuals to this so it is shown on schedule this gives a duration percent complete of 8.45%
( we want to compare duration % complete on the baseline against the current plan duration % complete )
Can anyone tell me why in P3e when i attach the baseline, the duration percent complete on the baseline changes and matches identically to the current schedule and shows 4.5% although when it is detached it shows 8.45 % ????
Also, what is Schedule Percent Complete
Regards
confused guest !