I have entered a task which I know will take one day and I want to show it taking place within a four day period eg duration of task 1 day start date 4th May and end date 7th May. The task may be done on either 4th, or 5th or 6th or 7th but will only take one day.
Please help as I know I have done this in the past!
Thanks a lot