I want to be able to have a budgeted cost, an actual cost, and the variance. I have been able to do this using baseline, total cost, and variance, but I need to be able to have this data on a task usage graph, that will spread the three across a timescale chart (by week). I would prefer not to have to deal with percentage complete.
I have removed the “actual costs are always figured by ms project” function, but I think that the problem is that I am possibly using the wrong fields for the information.
Any insight that you can offer would be greatly appreciated.
I have removed the “actual costs are always figured by ms project” function, but I think that the problem is that I am possibly using the wrong fields for the information.
Any insight that you can offer would be greatly appreciated.