Is there a way in P3 to have a task scheduled by saying, "Start date of this task is finish-start to when the first two of the following five tasks have been completed?"
This is required for production logic when step two of a process requires two batches of intermediate product from 5 batch plants. The 5 batch plants are independent, so the second process can start when any two are complete.
This is required for production logic when step two of a process requires two batches of intermediate product from 5 batch plants. The 5 batch plants are independent, so the second process can start when any two are complete.