I have a problem. I´m using Project 2000 and I´m tracking a construction project.
I typed the percent complete and saved the new baseline. So, suddenly, after the saving process end, the percents TURN BACK to old values.
After almost get crazy, in several tries, the changing stopped when I changed the task type to fixed units. But, why?
I don´t know why and I´d like to. The task type for whole project is fixed duration and I´m not using any resources.
Why it´s happening?
How it´s possible the baseline saving process to change the percent complete values?
Please, somebody, help me.
I typed the percent complete and saved the new baseline. So, suddenly, after the saving process end, the percents TURN BACK to old values.
After almost get crazy, in several tries, the changing stopped when I changed the task type to fixed units. But, why?
I don´t know why and I´d like to. The task type for whole project is fixed duration and I´m not using any resources.
Why it´s happening?
How it´s possible the baseline saving process to change the percent complete values?
Please, somebody, help me.