Thanks Phil, I was beginning to doubt my sanity. Too bad about conditional branching, I view that as a significant loss. Nice to be able to go directly from P6.7 to PRA, but can see some real value of conditional branching in 'what-ifs'. Not skilled enough in VB to address the issue. Again, thanks.
PS: Yes, I did miss the 8.6 to 8.7 discussion.
Member for
20 years 11 months
Member for21 years
Submitted by Philip Rawlings on Fri, 2011-03-11 16:29
This is a large and serious topic. You have obviously missed the discussion as it arose between versions 8.6 and 8.7.
In PRA now there are no extra modules - everything is built in e.g. Risk Factors and Weather Module.
The conditional branching uou remember was implemented by using VBA which was delivered along with Pertmaster. For various reasons, VBA cannot now be included with PRA, hence the removal of the tutorial. You can still do that sort (any many other sorts) by using VBA in Excel or VB or C++ (you can usee VB6 20101 Express which is free) as the COM 'hooks' are still there in PRA, but it is very much slower as the interface is external rather than internal. You could in theory go back to 8.6 which has VBA (if you can find it) but then you lose the bug fixes.
Not satisfactory I know; I have been fighting this one since October 2009.
Member for
18 years 6 monthsThanks Phil, I was beginning
Thanks Phil, I was beginning to doubt my sanity. Too bad about conditional branching, I view that as a significant loss. Nice to be able to go directly from P6.7 to PRA, but can see some real value of conditional branching in 'what-ifs'. Not skilled enough in VB to address the issue. Again, thanks.
PS: Yes, I did miss the 8.6 to 8.7 discussion.
Member for
20 years 11 monthsHi Dennis This is a large and
Hi Dennis
This is a large and serious topic. You have obviously missed the discussion as it arose between versions 8.6 and 8.7.
In PRA now there are no extra modules - everything is built in e.g. Risk Factors and Weather Module.
The conditional branching uou remember was implemented by using VBA which was delivered along with Pertmaster. For various reasons, VBA cannot now be included with PRA, hence the removal of the tutorial. You can still do that sort (any many other sorts) by using VBA in Excel or VB or C++ (you can usee VB6 20101 Express which is free) as the COM 'hooks' are still there in PRA, but it is very much slower as the interface is external rather than internal. You could in theory go back to 8.6 which has VBA (if you can find it) but then you lose the bug fixes.
Not satisfactory I know; I have been fighting this one since October 2009.
You can find more discussion on the Pertmaster User Group at http://tech.groups.yahoo.com/group/pertmaster/
Phil Rawlings
Euro Log Ltd