Primavera Project Planner - P3 Member for 21 years Member for 21 years 1 month Submitted by David Kelly on Mon, 2007-08-27 09:55 Permalink RE: Resource Salary In order to put fixed costs into the plan you should put the PRICED version of the resource against a hammock activity. Remember the "Freeze resource units per time period" switch in the autocost rules. Log in or register to post comments
Member for 21 years Member for 21 years 1 month Submitted by David Kelly on Mon, 2007-08-27 09:55 Permalink RE: Resource Salary In order to put fixed costs into the plan you should put the PRICED version of the resource against a hammock activity. Remember the "Freeze resource units per time period" switch in the autocost rules.