Resources on Summary Bars

Member for

19 years 11 months

David,



The easy way is to insert an activity and change the type to WBS instead of task and then schedule, there is no need for any links and this will be similar to the summary bar and you can assign resources to this activity with your lag and duration for each resource as normal.





Kind Regards

Mohamed

Member for

20 years 7 months

try and use a hammock activity.

start-start to first activity in schedule,
finish-finish to last activity in schedule.
activity type: hammock.

it is good practice to link the start and ends to milestones.

Gün.