Primavera Project Planner - P3 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alex Wong on Mon, 2006-12-18 20:50 Permalink RE: Average of all resources Hi Ijaz to do that you can use the resource layout, in the display options you select hrs only resouces then divid it by 8 or what every no of hr per day. Then in the time scale select you want your average by months or day or week or year. then in the histogram it will display your average manpower Good Luck Alex Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alex Wong on Mon, 2006-12-18 20:50 Permalink RE: Average of all resources Hi Ijaz to do that you can use the resource layout, in the display options you select hrs only resouces then divid it by 8 or what every no of hr per day. Then in the time scale select you want your average by months or day or week or year. then in the histogram it will display your average manpower Good Luck Alex
Member for
22 years 9 monthsRE: Average of all resources
Hi Ijaz
to do that you can use the resource layout, in the display options you select hrs only resouces
then divid it by 8 or what every no of hr per day.
Then in the time scale select you want your average by months or day or week or year.
then in the histogram it will display your average manpower
Good Luck
Alex