WBS

Member for

24 years 7 months

Go to http://www.primavera.com/customer/index.asp and register, you will need a P3 license that is in maintenance to register. After registering you will have access to the database, do a search on the number below and you will be able to download the files.



This spreadsheet is for P3 Ver 3.1 not Primavera Version 5.0.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Member for

19 years 1 month

Hi Paul,



First i would like to thank you for your book "Planning & scheduling using p5" it made it simple to me.



Can you explain how can i access the spreadsheet from primavera web site ?



Regards,



Moe

Member for

24 years 7 months

The copy function in the WBS form is designed to copy an arm of a WBS structure.



The is also a Excel spreadsheet available that may be used to import and export WBS Codes and Descriptions available from the P3 web site under Solution ID: 200252492644.



The other option is to use Batch but the spreadsheet is a lot simpler.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Member for

21 years 5 months

Likaa



Select the WBS code you wish to copy, then paste it. Simple!

P3 will ask for a new code value for the copied part.

Member for

22 years 9 months

export your activity list with wbs

copy and paste in Excel for all the wbs no

import back to p3



hth



alex