Wt. Factor in P3??

Member for

21 years 1 month

Hello Mr. Ronald Quilao,

Well you can do one thing for weightage factor Follow this method.



Suppose you have resource loaded programme and you know the budgeted quantity of the resource manhours.



If you want to do it automatically, Insert a new resource Manhours and insert the total manhours for the activity.



Once you get total manhours. remove the rest of the resources from the programme and just keep MHRS as the resource. Of make a copy of the resource loaded programme.

This will create a new schedule with only resource manhours. U can set it up as target to the complete resource loaded programme and then update it automatically of actuals to get the spended value against the expected value.

You can summarize the programme using summarization rule of resource units.



Regards,



Amit

Member for

22 years 3 months

Thank you guys!



Actually I already did those...in excel format...that was easy...but the client don’t want that method either.



I did tried also the Global Change but to no avail...maybe because the system has a difficulty in analysing or calculating my detailed entries (Multiple or rather complete (discipline) manpower)



Thanks once again.



Ronald

Member for

22 years 9 months

Ronald



What you need is a CDI to calculate your Weighted Man hr



However the system will not able to roll up to the format of your Layout grouping.



so what I normally do is export to excel and then calculate and display the weighting summary with the format I like



HTH



Alex

Member for

22 years 10 months

I believe that you could define a Global Change to do that. Then just execute that GC after calculating the CPM.