Retained Logic Question

Member for

22 years 11 months

Sunil, perhaps it may be a calendar phase problem. Check the calendars for any FF predecessors (I suppose ancestors is a better word - you may have to check several tasks preceding) to see if they are delaying the task (even though the predecessor is completed).



I remember seeing this problem on some scheduling system back when I was doing some testing, but I honestly don’t recall which system exhibited this behavior.



Bernard Ertl

eTaskMaker Project Planning Software

Member for

24 years 10 months

It could be that your program is linking percent complete to remaining duration.

Member for

24 years 6 months

Check constraints, suspend and resume dates and calendar of 90% complete activity.



If using Projects within Project Groups check advanced scheduling options re Data dates.



There has to be a logical reason and I consider progress overide fairly dangerous for the reason I explained before.