I dont have a constraint and milestone. But when I copied the whole program and worked in another system it works perfectly, but with february 1 as data date instead of March 1 which was set in my first PC
Member for
21 years
Member for21 years
Submitted by Philip Jonker on Thu, 2005-03-03 09:46
I was of for a while bit of a meduical problem, not serious.
What I am thinking is what you are saying, otherwise with milestones that are not correcrly set, you sometimes get this problem. Another one is Sundarams suggestion that the problem might be a sub-project that has an earlier data date.
I had a problem the first time I ran P3 under Windows XP, but it was not this problem. I know there is a patch for XP.
Regards,
Philip.
Member for
21 years 2 months
Member for21 years2 months
Submitted by Jaco Stadler on Thu, 2005-03-03 08:00
As Philip has adviced this probable mean you have a constraint what your logic is pushing but due to the constraint it has to take up the time some how remember it is only a program
Hi Philip welcome back long time.
Cheers
Member for
22 years 2 months
Member for22 years2 months
Submitted by Sundaram Arunan on Thu, 2005-03-03 08:00
Member for
20 years 8 monthsRE: Wrong EF date
I dont have a constraint and milestone. But when I copied the whole program and worked in another system it works perfectly, but with february 1 as data date instead of March 1 which was set in my first PC
Member for
21 yearsRE: Wrong EF date
Hi Jaco,
I was of for a while bit of a meduical problem, not serious.
What I am thinking is what you are saying, otherwise with milestones that are not correcrly set, you sometimes get this problem. Another one is Sundarams suggestion that the problem might be a sub-project that has an earlier data date.
I had a problem the first time I ran P3 under Windows XP, but it was not this problem. I know there is a patch for XP.
Regards,
Philip.
Member for
21 years 2 monthsRE: Wrong EF date
What is your late dates.
What is the TF. (Negative)
As Philip has adviced this probable mean you have a constraint what your logic is pushing but due to the constraint it has to take up the time some how remember it is only a program
Hi Philip welcome back long time.
Cheers
Member for
22 years 2 monthsRE: Wrong EF date
I have checked in one of my schedule which gives correct result.
For your problem i think it may be due to any other subproject id which might have been linked with this current project schedule
Member for
21 yearsRE: Wrong EF date
Do you have any constraint on these activities? Are they Milestones?