Wrong EF date

Member for

20 years 8 months

I don’t have a constraint and milestone. But when I copied the whole program and worked in another system it works perfectly, but with february 1 as data date instead of March 1 which was set in my first PC

Member for

21 years

Hi Jaco,

I was of for a while bit of a meduical problem, not serious.



What I am thinking is what you are saying, otherwise with milestones that are not correcrly set, you sometimes get this problem. Another one is Sundaram’s suggestion that the problem might be a sub-project that has an earlier data date.

I had a problem the first time I ran P3 under Windows XP, but it was not this problem. I know there is a patch for XP.





Regards,



Philip.

Member for

21 years 2 months

What is your late dates.

What is the TF. (Negative)

As Philip has adviced this probable mean you have a constraint what your logic is pushing but due to the constraint it has to take up the time some how remember it is only a program



Hi Philip welcome back long time.



Cheers

Member for

22 years 2 months

I have checked in one of my schedule which gives correct result.



For your problem i think it may be due to any other subproject id which might have been linked with this current project schedule


Member for

21 years

Do you have any constraint on these activities? Are they Milestones?