Planning, Scheduling & Programming Discussion Member for 9 years 8 months Member for 9 years 9 months Submitted by David Kelly on Mon, 2023-08-28 14:54 Permalink You should always zero fill You should always zero fill in P6. For example, a WBS code should be DAM.3.4.01 not DAM.3.4.1 Just overtyping the WBS code with the new zero filled values should sort it Log in or register to post comments
Member for 9 years 8 months Member for 9 years 9 months Submitted by David Kelly on Mon, 2023-08-28 14:54 Permalink You should always zero fill You should always zero fill in P6. For example, a WBS code should be DAM.3.4.01 not DAM.3.4.1 Just overtyping the WBS code with the new zero filled values should sort it
Member for
9 years 8 monthsYou should always zero fill
You should always zero fill in P6.
For example, a WBS code should be DAM.3.4.01 not DAM.3.4.1
Just overtyping the WBS code with the new zero filled values should sort it