If the Schedule data date is April 29, you should not record any Actual Dates on or after April 29. Calculating the schedule with such Actual Dates generates erroneous dates for all activities on the successor string of that activity.
You can determine if you did record such Actual Dates within the Schedule Report - generated by choice when you calculate the new schedule dates. There is a line in the early part of the report that states the number of Actual Dates > than the Data Date. This tells you if such Actual Dates exist. Then just run a filter for such dates and correct.
Member for
16 years 11 months
Member for17 years
Submitted by Mike Sallese on Tue, 2022-06-14 13:43
If the Schedule data date is April 29, you should not record any Actual Dates on or after April 29. Calculating the schedule with such Actual Dates generates erroneous dates for all activities on the successor string of that activity.
You can determine if you did record such Actual Dates within the Schedule Report - generated by choice when you calculate the new schedule dates. There is a line in the early part of the report that states the number of Actual Dates > than the Data Date. This tells you if such Actual Dates exist. Then just run a filter for such dates and correct.
Member for
10 years 5 months
Member for10 years5 months
Submitted by Ahmad Abdrabou on Fri, 2022-06-10 20:48
if you are wroking from 8:00 AM to 5:00 PM, and showing time in hours in the schedule, then you can start the activity on 8:00 AM and put the Data Date to 5:00 PM on the same day (Assuming it's a Working Day). After scheduling the Actual Duration will show 1 day (not 5 days).
Regarding to Schedule % Complete:
Consider the above setup, and after scheduling, go to project tab and assign the Data Date to a later date (without scheduling) it will change the Schedule % Complete value.
Regarding to Actual Duration:
It's uneditable, you can't change it unless you start the Activity and schedule the Data Date.
Regards,
Ahmad.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Mon, 2022-06-06 15:09
2. scheduled % complete is just that SCHEDULED how much SHOULD have been done SCHEDULED TO HAVE BEEN COMPLETED.
3. It this activity is on the critical path then the float is greater than -39 days negative so the negative value wil lbe greater than -39 meaning MORE negative.
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Fri, 2022-06-03 15:10
Duration % Complete = The percent complete of the activity duration. Computed as (Original Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Original Duration is taken from the current plan, not from the baseline.
Schedule % Complete = The activity schedule percent complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the baseline Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline.
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Fri, 2022-06-03 01:13
Member for
16 years 11 monthsIf the Schedule data date is
If the Schedule data date is April 29, you should not record any Actual Dates on or after April 29. Calculating the schedule with such Actual Dates generates erroneous dates for all activities on the successor string of that activity.
You can determine if you did record such Actual Dates within the Schedule Report - generated by choice when you calculate the new schedule dates. There is a line in the early part of the report that states the number of Actual Dates > than the Data Date. This tells you if such Actual Dates exist. Then just run a filter for such dates and correct.
Member for
16 years 11 monthsIf the Schedule data date is
If the Schedule data date is April 29, you should not record any Actual Dates on or after April 29. Calculating the schedule with such Actual Dates generates erroneous dates for all activities on the successor string of that activity.
You can determine if you did record such Actual Dates within the Schedule Report - generated by choice when you calculate the new schedule dates. There is a line in the early part of the report that states the number of Actual Dates > than the Data Date. This tells you if such Actual Dates exist. Then just run a filter for such dates and correct.
Member for
10 years 5 monthsHello,Regarding to Data Date
Hello,
Regarding to Data Date and Start Date:
if you are wroking from 8:00 AM to 5:00 PM, and showing time in hours in the schedule, then you can start the activity on 8:00 AM and put the Data Date to 5:00 PM on the same day (Assuming it's a Working Day). After scheduling the Actual Duration will show 1 day (not 5 days).
Regarding to Schedule % Complete:
Consider the above setup, and after scheduling, go to project tab and assign the Data Date to a later date (without scheduling) it will change the Schedule % Complete value.
Regarding to Actual Duration:
It's uneditable, you can't change it unless you start the Activity and schedule the Data Date.
Regards,
Ahmad.
Member for
16 years 3 months1. you can not have ANY
1. you can not have ANY actuals on the data date
2. scheduled % complete is just that SCHEDULED how much SHOULD have been done SCHEDULED TO HAVE BEEN COMPLETED.
3. It this activity is on the critical path then the float is greater than -39 days negative so the negative value wil lbe greater than -39 meaning MORE negative.
Member for
19 yearsP6 formula for :Duration %
P6 formula for :
Duration % Complete = The percent complete of the activity duration. Computed as (Original Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Original Duration is taken from the current plan, not from the baseline.
Schedule % Complete = The activity schedule percent complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the baseline Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline.