yes out of sequence logic and be viewed in the P6 log report.
you can have logic pushing through an activity ie.
Activity A B and C all sequential
Activity A is in progress
Activity B is completed
Activity C has not started
Since activity A is not complete the earliest that activity C can begin is when activtiy A is done. Even though activity A is not tied to activity C it is still honoring the retained logic and passes thru activity B to activity C
Member for
16 years 3 monthsyes out of sequence logic and
yes out of sequence logic and be viewed in the P6 log report.
you can have logic pushing through an activity ie.
Activity A B and C all sequential
Activity A is in progress
Activity B is completed
Activity C has not started
Since activity A is not complete the earliest that activity C can begin is when activtiy A is done. Even though activity A is not tied to activity C it is still honoring the retained logic and passes thru activity B to activity C