When you import the XER as supplied, do you lose all Cost Data as stated in your initial comment, or just some / incorrect data?
After Unlinking the Units & Costs, are you now seeing Cost Data, but not the expected values?
Have you checked for Duplicate Resources on the xer file provided? Primavera seems to struggle where there are duplicate resources assigned to the same activities unless they have different cost account ID's.
When Importing it can cause the duplicated resource to overwrite the first value entered.
Unfortunately you would need to either check the XER file to identify this issue (as the value is already lost on import to P6) or import as a new project & change the Activity Resource Assignments import option from Update Existing to Insert New. You can then compare these values to see if they are now displaying what you expect.
Another thing I have found is that if you import an XER file without changing the Import Options, then it does not seem to import all the data from the XER file as you would expect.
When you get to the Update Project Options section of the Import Process, if you do not make any changes to this selection then it may cause issues with the import (e.g. Activity Notebooks / Steps not updating correctly). If you click on the Modify button & then OK (without making any changes) then it seems to take in all the missing data - not managed to figure out why this is the case. This is the same section that Zoltan is referring to.
Regards,
Steven
Member for
10 years 7 months
Member for10 years7 months
Submitted by jalberthenet on Mon, 2021-02-15 14:13
Thank you for your reply Zoltan , I have not had much luck sorry - see below.
1st see if you have the security rights to import costs
>>> please share where I can confirm this ?
2nd that global change only works on projects that are opened
>>> yes confirmed , the error still appears while trying to apply write the change.
3rd when importing the xer file when you get to the Update Project Options select modify and and in the Data Type" Global section make sure that for the Resources group that the action item is INSERT NEW
>>>> again, confirmed this option was selected , but the budgeted cost field remained zero after importing....
Any other ideas ? :)
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Mon, 2021-02-15 14:11
1st see if you have the security rights to import costs
2nd that global change only works on projects that are opened.
the global change should be
where Calculate costs from units equals Yes
Then Calculate costs from units - No
if you are using version 18 this is a bug that you need the patch for
3rd when importing the xer file when you get to the Update Project Options select modify and and in the Data Type" Global section make sure that for the Resources group that the action item is INSERT NEW
Member for
16 years 3 monthsrigth can be found under
rigth can be found under Admin
Then on the project profiles whatever the default box is checked should be administrator
then in the bottom section under Previlege
ALL HAS PREVILEGE SHOULD BE Checked
also up top on the left on Global profiles the default box checked should be Administrator maybe
then in the bottom section under Previlege
ALL HAS PREVILEGE SHOULD BE Checked
Also Admin Users
on the global access tab
under Global Security Profile
it should be <Admin Superuser>
Member for
8 years 1 monthCould you please clarify a
Could you please clarify a few things.
When you import the XER as supplied, do you lose all Cost Data as stated in your initial comment, or just some / incorrect data?
After Unlinking the Units & Costs, are you now seeing Cost Data, but not the expected values?
Have you checked for Duplicate Resources on the xer file provided? Primavera seems to struggle where there are duplicate resources assigned to the same activities unless they have different cost account ID's.
When Importing it can cause the duplicated resource to overwrite the first value entered.
Unfortunately you would need to either check the XER file to identify this issue (as the value is already lost on import to P6) or import as a new project & change the Activity Resource Assignments import option from Update Existing to Insert New. You can then compare these values to see if they are now displaying what you expect.
Another thing I have found is that if you import an XER file without changing the Import Options, then it does not seem to import all the data from the XER file as you would expect.
When you get to the Update Project Options section of the Import Process, if you do not make any changes to this selection then it may cause issues with the import (e.g. Activity Notebooks / Steps not updating correctly). If you click on the Modify button & then OK (without making any changes) then it seems to take in all the missing data - not managed to figure out why this is the case. This is the same section that Zoltan is referring to.
Regards,
Steven
Member for
10 years 7 monthsThank you for your reply
Thank you for your reply Zoltan , I have not had much luck sorry - see below.
1st see if you have the security rights to import costs
>>> please share where I can confirm this ?
2nd that global change only works on projects that are opened
>>> yes confirmed , the error still appears while trying to apply write the change.
3rd when importing the xer file when you get to the Update Project Options select modify and and in the Data Type" Global section make sure that for the Resources group that the action item is INSERT NEW
>>>> again, confirmed this option was selected , but the budgeted cost field remained zero after importing....
Any other ideas ? :)
Member for
16 years 3 months1st see if you have the
1st see if you have the security rights to import costs
2nd that global change only works on projects that are opened.
the global change should be
where Calculate costs from units equals Yes
Then Calculate costs from units - No
if you are using version 18 this is a bug that you need the patch for
3rd when importing the xer file when you get to the Update Project Options select modify and and in the Data Type" Global section make sure that for the Resources group that the action item is INSERT NEW