page 24: 4. Resource Curves. The scheduler can use P6 to define how to allocate the resource utilization over the duration of the activity. This is normally not a resource leveling issue because P6 resource leveling does not currently consider resource curves when resource leveling. P6 just uses an even daily distribution for resource leveling.
As far as I can recall the use of resource curves is recommended for initial summary planning with no automatic leveling.
If using Spider Project the software can automatically level for variable quantities taking into consideration how production rates might change.
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Tue, 2020-09-01 20:22
by deafult the resource distribution is a linear function menaing it spreads the budgeted amout over the activity evenly
what you can do is assign a resource curve to the activity or create your own curve to tell it how you want to distribute the resources over the duration front loaded, back loaded, triangular
go to the activit then to the resource tab at the bottom
right click and select customize resource columns and expand the General category and select curves
from there you will see a list of different curves select the one that you want and assign that curve ot that activity.
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Sun, 2020-08-30 19:09
Member for
21 years 8 monthsIf using P6 be reminded that
If using P6 be reminded that P6 consider an even daily distribution for resource leveling therefore your leveling might still be overallocated.
If using Spider Project the software can automatically level for variable quantities taking into consideration how production rates might change.
Member for
21 years 8 monthsPlease be reminded that
Please be reminded that billings should cover costs of idle resources and these hidden costs must be tracked and managed as not to loose money.
Member for
16 years 3 monthsby deafult the resource
by deafult the resource distribution is a linear function menaing it spreads the budgeted amout over the activity evenly
what you can do is assign a resource curve to the activity or create your own curve to tell it how you want to distribute the resources over the duration front loaded, back loaded, triangular
go to the activit then to the resource tab at the bottom
right click and select customize resource columns and expand the General category and select curves
from there you will see a list of different curves select the one that you want and assign that curve ot that activity.
Member for
15 years 11 monthsSometimes the Comments have a
Sometimes the Comments have a lot of meaning because it depends on the interpretations of every reader.
Can you provide the texts of the comments?
Member for
15 years 11 monthsSometimes the Comments have a
Sometimes the Comments have a lot of meaning because it depends on the interpretations of every reader.
Can you provide the texts of the comments?