Forecast Schedule

Member for

15 years 11 months

Hi.

The issue is due to out of sequence. Trace the predecessors of predecessors of predecessors of activities that slips beyond project baseline completion date.

Member for

16 years 3 months

1. do as Raymund suggest

2 .filter for any selected filter

and select both the 3rd and 4th ones in the list 

has start constraint

has finish constraint

these are activities with hard constraint dates if you do not need them remove them

3. filter for remaining durations over 20 days you could have made a typo in the remaing durations.

Member for

6 years 11 months

Thanks for your response.

Actually I already done that and no negative float appears. One thing is that the forecast dates are now way beyond the original project completiion dates. As I trying to change the dates of some activities some are not moving even I have chnage the relationship or changing the lag.

 

Thanks

Member for

15 years 11 months

Hi,

As I understand from you, you want to get rid of the Negative Float (-166).

In the Projects Pane:

1. Select the Project

2. In the Project Details, Select Dates

3. Clear the Date shown in the "Must Finish By"

Or In the Activity Pane:

1. Trace the Activities with -166 Total Float and Clear the assigned Contraints.

 

Hope this will help